13/12/2010

Kristina’s kidding PM

Filed under: Governance,People,Risk,Standards — lenand @ 8:14 am
Tags: , , , ,

The director in charge of the Prime Minister’s Implementation Unit would appear to be Kristina Murrin. Her own agents proudly proclaim her initial qualifications as “… educated at Cambridge University, where she read Social and Political Sciences, specialising in child psychology“.  I have great respect for her excellent credentials:  “She is co-author of a book, Sticky Wisdom: How to Start a Creative Revolution at Work, that urges workers to “build a personal bravery plan”, “fill their minds with freshness” and “stop sending memos”.“, reports the Telegraph.

Unkowingly, there may be some substance in Quarkside’s original criticism of the Structural Reform Plans progress, “This is primary school level planning, not the way to control a national reform programme.” Child psychology and abolition of memos have never, to my knowledge, featured in any training course on Programme Management.  She may have great value as an inspirational speaker and Departmental Director, but from the evidence Quarkside has seen, unlikely to have directed a major programme in the private or public sector.

The risk is that inspiration completely overwhelms the perspiration and plodding needed from the ranks below the leader.  The last thing we want for transparency is creative spinning of uncorroborated ‘evidence’.  The predictable problems of kiddy control could be avoided by the appointment of a hard-nosed programme director who can winkle out risks and publish professional progress reports.  Programme management needs standards.

Any volunteers to become the new Government CIO?

10/12/2010

SRPs avoid PM standards

As Quarked previously, the baseline (Draft) Structural Reform Plans (SRPs) for each Department are almost acceptable. There’s just about enough to begin a reasonable job of monitoring and control. There are actions with start dates and end dates. There are also milestones.

What is missing are definitions of what has to be delivered by an end-date. Quarkside believes that all public sector projects are expected to use Prince2 for project management. It is almost written in stone in Local Government. As everybody who has been trained knows, Prince2 “Focuses on products and their quality“.  In other words it is ‘Product based planning’.  A plan is only considered complete when it has described WHAT should be DELIVERED by a specific date, WHO should deliver it and the QUALITY criteria for acceptance.  All these points rely a documented and agreed Prince2 Product Description.

Number 10’s Implementation Unit have misunderstood the guidelines, or have chosen to avoid them. You can identify a product deliverable because it is (usually) a concrete noun in the Product Breakdown Structure. The SRPs use a verbal description of an action eg Home Office

  • 3.2.ii “Introduce English language requirements for spouses”.

Are these requirements a statute, a regulation or a ministerial memo to the Immigration and Nationality Directorate? Delivery implies the complete acceptance of a specific product. An alternative might be:

  • 3.2.ii “English Language regulations agreed by Parliament and applied in Border Control”

Quarkside is not making a political point or just being pedantic. The first definition has many options on what the end product might be; the second is more specific and would be linked to the Product Description.   In fact 3.2.ii in the Draft SRP does not give an end date, showing uncertainty.  Prince2, using Product Flow Diagrams, would enable an end-date to be calculated.

Action based planning must have its devotees.  Notably that’s the path followed by Microsoft Project out of the box.  MS Project, unsurprisingly, does not follow the UK standard but is easy to tailor for Prince2 methods.

Martha Lane Fox has called for the use of standards  Not only does it increases the interoperability project managers, it is the most effective way of controlling projects.   The good news is that it is not be a big problem to change the Draft SRPs and produce a Prince2 plan with a useful Product Breakdown Structure.  When this process is done it always uncovers things that had originally been considered.  It improves the Plan.

The current Plan is little more than a ToDo list.  That style is suitable for planning a foreign holiday for a group of thirteen people. It is not suitable for the far reaching political reforms of the coalition government. Prince2 is the Standard.  The No 10 Implementation Unit should have ensured that each of the thirteen Departments understood and used Prince2 for both the Plan and the control mechanisms.

It’s not too late to produce a final plan that follows the Prince2 Standard.  Then we can produce a transparent monitoring and control process.

09/12/2010

No 10: SRP shambolic progress

Filed under: Policy,Politics,Process,Risk — lenand @ 9:17 am
Tags: , , , , , , , , , , , , , , , , ,

The Prime Minister launched 13 draft Structural Reform Plans (SRPs) in June.  Departments set out their reform priorities and the actions they would have to take to achieve them, including a specified timetable and measurable milestones. Under the initiative each department had to produce a monthly progress report, holding the Secretary of State to account to the Prime Minister if they are not on track.  Quarkside has not studied all in detail, but the structure of the plans looks sound.  There is a consistent layout and it is easy to see what is expected.

However the monthly updates are shambolic.  Granted the layout is consistent but they do not conform to best practice in progress reports.  With the intention to increase transparency, they are more likely to obfuscate than clarify. Some examples to illustrate this career threatening statement may elucidate:

  • The reference numbers are not carried forward, it is difficult to know which deliverable a progress line refers to.  All good systems would refer to a Product Breakdown Structure (PBS) number for ease of reference.
  • Missed target lines are in red, but they don’t give any indication of the changed date or the action to be taken to recover the plan.  This is not control, it is an ineffective observation.
  • The status column only has a choice of complete, not complete, not started, work started, work ongoing. and still not complete.  This is primary school level planning, not the way to control a nation reform programme.
  • The reasons for failure to meet targets look more like excuses and not a lot of value.  They just lose credibility without plans to get the programme back on track.
  • There is no risk register to give any idea of the seriousness of any delays.  Every project needs a risk register – it looks like the product of amateurs, not professionals.

That’s the bad news. Looking at the Quarkside principles, the Process is bad, the Governance is pathetic and the Technology is antiquated.  Could we respectfully request that the Prime Minister’s Delivery Unit takes some crash courses in effective Programme Management Office (PMO) processes.

The good news is that is all recoverable. Watch Quarkside for some answers in future blogs.